|
Home
> Nautical Information
Testing
Continues on the Next Generation Propulsion System
By Leslie Spaulding - July 2000 Excerpt
A major component of Secretary of the
Navy Richard Danzig's June 1 visit to Philadelphia was
the Integrated Power System Land Based Engineering (IPS
LBES). Danzig announced the Navy's endorsement of IPS
for use in the 21st Century Land Attack Destroyer (DD
21) in early January. Following his tour of the test
site, he stated "The revolutionary advances associated
with IPS and electric drive would not have been possible
without the existence of this highly-capable test facility
in Philadelphia and the engineering 'know-how' of our
dedicated Navy-industry team."
This
"highly-capable test facility" is in its second
phase of testing to complete the full-scale advanced
development phase of IPS. The IPS incorporates electric
propulsion and ship service electrical distribution
into a single integrated system, allowing power to be
sent wherever it is needed. The efficient use of power
with IPS will result in significant fuel and maintenance
savings aboard U.S. Navy ships, as well as increased
flexibility for future design modifications and weapon
system upgrades through rapid technology insertion as
existing hardware becomes obsolete. The IPS is expected
to benefit the Navy by reducing ownership and construction
costs and improving survivability and Naval architecture
flexibility.
The
initial phase of testing ran from April through June
1999. This testing consisted of operating all available
IPS-associated equipment simultaneously to evaluate
total system performance. Based, in part, on this proof
of concept, the Navy and the DD 21 industry teams decided
that IPS would be ready for Fleet introduction. Following
this initial phase, the main IPS generator was removed
to accommodate installation of the Intercooled Recuperated
(ICR) Gas Turbine. The ICR tests ran from October through
December 1999. The site was once again changed out to
accommodate the IPS testing, and the IPS generator was
brought back on line in early April 2000.
Currently,
the site is being used to test the ships service distribution
system as a stand-alone portion, using a utility feed.
The IPS testing has resulted in continued Code 80/90
teaming. Some of the ship service distribution system
components were originally developed by Code 80 while
they were located in Annapolis, and 80 and 90 teamed
to successfully transition this hardware to the IPS
LBES. Now, actual IPS test data is being incorporated
into a Code 80 impedance model of the ship service distribution
system. Using this model, Code 80 will be able to predict
how the system will perform and whether or not there
are instabilities in the regions of operation.
"Based
on actual test data, Code 80 will be able to make their
model more accurate," said Matt Stauffer, IPS LBES
Program Manager. "The goal is that they will be
able to predict the performance of next generation systems
based on a validated model." Working together on
the joint 80/90 project were John Johnson (814), Johnson
Yuen (813), Jerome Thomas (814), Tom Fikse (812), Rashid
Fazal (811), Neil Hiller and Rich Zalewski (both of
934).
The
next step in IPS testing is to bring some of the more-recently-developed
power conversion modules on line with the propulsion
motor and prove all the equipment that was delivered
under the IPS contract. This phase of testing is expected
to run through January 2001.
The
site will then be used to test the next generation of
power conversion modules. The Navy IPS Office is currently
developing these modules. Basically, what is being tested
now represents about 30% of the power conversion hardware
that would be found on a destroyer with an IPS architecture.
With this next generation testing, IPS will be used
to power approximately 60% of the power conversion hardware.
This equipment represents three zones aboard ship. "The
main reason we're going to do the three zones is to
perform better fault testing," said Stauffer. "We
will simulate the ship taking a hit by short-circuiting
one zone and prove that the adjacent zones stay on line.
We also plan to prove more automation." This testing
is slated for 2002 and 2003. The DD 21 Program has two
competing industry teams who are currently developing
system concept designs and life cycle engineering and
support proposals to meet DD 21's operational requirements.
The outcome of this competition is not known; however,
the fact that the ship will be powered by an integrated
power system is a given. The Advanced Propulsion and
Power Generation Test Site Section (9112) is pursuing
testing of DD 21 hardware following the award of the
contract.
For
More Information Contact:
Leslie
Spaulding at spauldingl@nswccd.navy.mil
or (215) 897-7702.

|